The City of Stratford is planning to rehabilitate the Kenner Crescent watermain using a Cured-in-place pipe (CIPP) lining technology.

CIPP lining is a cost-effective trenchless solution that lines the inside diameter of the existing pipe with a composite material. The stand-alone structural liner withstands loads and internal pressures without relying on the residual strength of the existing pipe.

The CIPP lining material is designed and manufactured to meet all drinking water requirements. One of the main benefits for this innovative technology is the substantial cost savings achieved by reducing open excavation and surface restoration.

The cleaning and lining method involves two processes. The first is scraping the inside of the main to remove accumulated mineral deposits. The second part of the work involves the installation of a structural liner inside of the freshly cleaned pipe.

The project map showing the work area is available in the Documents section at right.

If you have a comment or question about this project, please use the Questions/Comments tool below.

The City of Stratford is planning to rehabilitate the Kenner Crescent watermain using a Cured-in-place pipe (CIPP) lining technology.

CIPP lining is a cost-effective trenchless solution that lines the inside diameter of the existing pipe with a composite material. The stand-alone structural liner withstands loads and internal pressures without relying on the residual strength of the existing pipe.

The CIPP lining material is designed and manufactured to meet all drinking water requirements. One of the main benefits for this innovative technology is the substantial cost savings achieved by reducing open excavation and surface restoration.

The cleaning and lining method involves two processes. The first is scraping the inside of the main to remove accumulated mineral deposits. The second part of the work involves the installation of a structural liner inside of the freshly cleaned pipe.

The project map showing the work area is available in the Documents section at right.

If you have a comment or question about this project, please use the Questions/Comments tool below.

Ask Us a Question / Leave a Comment

Do you have a question about the Kenner Crescent Watermain Relining Project? 

Ask us here, and we will do our best to answer it as soon as possible.

Or, if you want to leave a comment, please feel free to do so.


loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Is it ok to use our water softener throughout the project? on Facebook Share Is it ok to use our water softener throughout the project? on Twitter Share Is it ok to use our water softener throughout the project? on Linkedin Email Is it ok to use our water softener throughout the project? link

    Is it ok to use our water softener throughout the project?

    MMVG asked 7 months ago

    Thank you for your question.

    Yes, you can continue to use your water softener throughout the project.

Page last updated: 18 Apr 2024, 10:23 AM